Power Generation

Project: GE 40 Megawatt Condensing steam turbine

Objective

Remove and refurbish turbine main stop valve.

 

Our Approach

  • Remove main stop valve assembly from a decommissioned plant
  • Disassemble, clean and inspect all MSV components
  • Remachine the MSV housing weld connections
  • Reassemble all components
  • Ship to new facility for installation

Our Outcome

  • Custom saved significant cost by implementation of a refurbished MSV solution
  • customer saved significant time by utilizing a refurbished part versus realizing a long lead times for a new MSV
  • Customer was back online sooner saving cost and lost revenue

 